Unit 13 – Project quality management
Copyright © 2015 Provek Limited 167 The Provek APMP Book v2-5
Exam practise questions
1. Explain five quality activities that are relevant within a project life cycle. (50 marks)
2. Explain each of the following terms:
(i) Quality management (10 marks)
(ii) Quality planning (10 marks)
(iii) Quality control (10 marks)
(iv) Quality assurance (10 marks)
(v) Continuous improvement (10 marks)
Copyright © 2015 Provek Limited 167 The Provek APMP Book v2-5
Exam practise questions
1. Explain five quality activities that are relevant within a project life cycle. (50 marks)
2. Explain each of the following terms:
(i) Quality management (10 marks)
(ii) Quality planning (10 marks)
(iii) Quality control (10 marks)
(iv) Quality assurance (10 marks)
(v) Continuous improvement (10 marks)